
Installation - Mechanical
14 CXRC-SVX01F-EN
Installation Preparation
Before installing the unit, perform the following
procedures to ensure proper unit operation.
1. Position the unit and skid assembly in its final location.
2. Test lift the unit to determine exact unit balance and
stability before hoisting it to the installation location.
See
“Unit Handling Procedure,” p. 13 for proper
rigging procedures and cautions.
3. Remove the skids from under the unit. See unit IOM
SCXF-SVX01*-EN, “Skid Removal” section. If you find
internal damage, file a claim immediately to the
delivering carrier.
4. Remove the protective shipping covers from the unit.
5. Verify isolators are properly tightened for operation.
See
“Unit Isolation,” p. 14.
Unit Isolation
The standard unit comes with 6” x 6” x 3/8” thick isolator
pads. Place these under the unit in the locations shown in
Figure 14, p. 15 through Figure 16, p. 15.
Spring Isolators
Unit mounting locations are shown in Figure 14, p. 15
through Figure 16, p. 15. Operating weights and weight
loading at each mounting location are provided in Table 5,
p. 14. Isolator placement instructions are also placed in the
control panel with other unit documentation. Isolators are
identified by spring color and by the isolator part number.
All units utilize CP-1-28 “green” isolators (20–32 ton units
use 4 isolators per unit, 35-40 ton units use 6, and 50–60
ton units use 8). Install spring isolators at each unit
mounting point using the following procedure:
1. Bolt the isolators to the mounting surface using the
mounting slots in the isolators base plate. Do not fully
tighten the isolators mounting bolts at this time.
2. Set the unit on the isolators: the isolator positioning
pins must register in the unit mounting holes. See
Figure 14, p. 15 through Figure 16, p. 15 for locations.
3. Ensure clearances between upper and lower isolator
housings are between ¼” to ½“. See isolator detail in
Figure 13, p. 14. A clearance of over ½” requires shims
to level the unit (see Leveling the Unit section on this
page).
4. Make minor clearance adjustments by turning the
isolator leveling bolt clockwise to increase clearance
and counterclockwise to decrease clearance.
If proper isolator clearance cannot be obtained by turning
the leveling bolt, level the isolators themselves. A ¼”
variance in elevation is acceptable.
NOTICE:
Equipment Damage!
Proper isolator clearance and unit level must be
achieved or structural damage may occur.
Figure 13. Typical CCRC/CIRC unit isolator CP-1-28
Table 5. Unit operating weight distribution at mounting locations
Unit Size Shipping Weight (lb) 1 2 3 4 5 6 7 8 Total Operating Weight (lb)
20 2030 463 463 463 517 1906
29 2084 490 463 490 517 1960
32 2138 490 490 490 554 2014
35 3018 463 463 463 463 463 518 2833
40 3072 463 463 490 463 463 518 2887
50 3995 490 490 490 490 490 350 490 405 3695
60 4275 490 490 490 490 490 490 490 545 3975
Note: Mounting locations referenced above correlate with mounting location shown in Figure 14, p. 15 through Figure 16, p. 15
Comentarios a estos manuales