VRF-SVN33A-EN 11
Unit Installation
Minimizing Vibration
When installing multiple mini outdoor units side by side, or when there is a need to minimize unit
vibrations, use a vibration-minimizing structure such as an H-beam frame or a vibration-isolation
frame, and an isolation pad. Refer to the specifications in Figure 5.
After installation, apply corrosion-protection to the frame.
Figure 5. Vibration-minimizing structure specifications
After installing a vibration-isolation frame, loosen the bolts so that the isolators are capable of
absorbing vibrations (Figure 6).
Figure 6. Bolts on vibration-isolation frame
Securing the Mini Outdoor Unit
The mini outdoor unit must be secured so that it can withstand a wind speed of 67 mph (30 m/s).
Secure the unit firmly to the base with M10 anchor bolts (see Figure 7).
Use zinc-plated or stainless steel nuts and bolts.
Use a rubber washer between the bolt and the unit to prevent bimetallic corrosion.
Outdoor unit
Anchor bolt with nut/spring/washer
Isolation pad minimum thickness: 1 in. (20 mm)
H-beam
3 in. (75 m m) min.
A: Width of unit mounting foot
1 in.
(20 mm)
Base
Isolation pad dimensions: A + 1/2 to 1 in. (10–20 mm) minimum
Ensure that
bolts are loose.