24 CAH-SVX01B-EN
Installation - Mechanical
TCP Base Section Assembly with Turned-Up Floor
1. See Figure 11. Apply 4-inch x ¼-inch neoprene gasket to the full perimeter face of each shipping
split section.
2. Join the two sections and secure with field-provided 5/8-inch flat washers and 5/8-inch x 2 ½-
inch grade 9 bolts through each of the six holes.
3. Apply a heavy bead of caulk to the inside of the U-channel.
4. Press U-channel down over upturned flanges with moderate pressure to ensure it is fully seated
onto upturned flanges. The caulk will cure and act as an adhesive to hold U-channel in place,
no fasteners are required.
Figure 11. Upturned floor assembly
Cap
Caulk
Floor
Cap
Caulk
Floor
Floor
Floor
Gasket
Gasket